Plan User Manual
Page 1 of 21
Plan for UIQ
(Sony Ericsson P800/P900, Motorola A1000,…)
User Guide
Version 3.00
Copyright © Twiddlebit Software 2004
All rights reserved.
Some of the names used within this manual and displayed by the software are registered
trademarks. Such names are acknowledged as trademarks even though they have not been
marked with the ® symbol.
Seitenansicht 0
1 2 3 4 5 6 ... 20 21

Inhaltsverzeichnis

Seite 1 - User Guide

Plan User Manual Page 1 of 21 Plan for UIQ (Sony Ericsson P800/P900, Motorola A1000,…) User Guide Version 3.00 Copyright © Twiddlebit Software 2004 Al

Seite 2 - INTRODUCTION

Plan User Manual Page 10 of 21 MPX file format Plan on the UIQ device can also directly read Microsoft Project MPX files. If making changes to an open

Seite 3 - Installation

Plan User Manual Page 11 of 21 KEY FEATURES Plan has the following key features:  A separate file for each project plan with either plan specific or

Seite 4 - Purchase Options

Plan User Manual Page 12 of 21  flexible repeating work shift pattern, e.g. standard start/end work hours Mon-Fri repeating every 7 days  override

Seite 5 - PROJECT PLANNING

Plan User Manual Page 13 of 21 VIEWS Plan supports the following views, all accessible from the toolbar:  Task list  Gantt view  Resource list 

Seite 6 - Calculation of task dates

Plan User Manual Page 14 of 21 Depending upon the zoom factor the time axis may show the years, months, weeks, days or hours. There is a maximum and m

Seite 7 - FAST START TUTORIAL

Plan User Manual Page 15 of 21 Use the two buttons on the toolbar to move from one half year to the previous/next. There are also two buttons which al

Seite 8 - Summary tasks

Plan User Manual Page 16 of 21 TASKS Editing tasks To create a new task position select a task where the new task is to be inserted (it will be insert

Seite 9 - Sample Plan

Plan User Manual Page 17 of 21  Target. This value is shown for reference and cannot be altered. It shows how much of the task should be complete at

Seite 10 - Page 10 of 21

Plan User Manual Page 18 of 21 Baselines (saved work/start/end date) Each task has a saved work/start/end date. This can be used to store a baseline f

Seite 11

Plan User Manual Page 19 of 21 RESOURCES Plan allows any number of resources to be created, subject to available memory. Each resource has a repeating

Seite 12 - Page 12 of 21

Plan User Manual Page 2 of 21 INTRODUCTION About this manual This manual describes how to use the Twiddlebit Plan project planning tool. This manual i

Seite 13

Plan User Manual Page 20 of 21 Notes:  User notes. Freeform note associated with the resource.

Seite 14 - Holiday view

Plan User Manual Page 21 of 21 CALCULATION SETTINGS AND PREFERENCES Calculation/Storage Settings  Calculation. May be set to “Automatic” or “Manual”

Seite 15 - Page 15 of 21

Plan User Manual Page 3 of 21 Installation Plan may be supplied in various forms: 1. Pre-installed on an MMC. In this case simply insert the MMC into

Seite 16

Plan User Manual Page 4 of 21 Purchase Options Plan is shareware, which means that if you continue to use it you should register with Twiddlebit. The

Seite 17 - Summary and sub-tasks

Plan User Manual Page 5 of 21 PROJECT PLANNING Fundamental concepts Plan allows a project plan to be constructed from individual task components. Task

Seite 18 - Page 18 of 21

Plan User Manual Page 6 of 21 Example Consider a task which is estimated to take two man days to complete, (one man day being the time between the sta

Seite 19

Plan User Manual Page 7 of 21 FAST START TUTORIAL This section describes, by way of an example, how to use the main features within Plan. It includes

Seite 20 - Page 20 of 21

Plan User Manual Page 8 of 21 Creating tasks Now enter a new task. From the toolbar select the “Task List” view (far left toolbar button). Select the

Seite 21

Plan User Manual Page 9 of 21 At the moment all the tasks are normal tasks and we need to make task 1 and 2 sub-tasks of the new task. To do this, mak